Understanding the Rapidly Evolving Horizon of Inteligent Buildings

Mitchell Britto, Director, Smart Building Services, TDIndustries

Understanding the Rapidly Evolving Horizon of Inteligent Buildings

Pioneering a Cloud-Ready Construction Ecosystem

Tooey Courtemanche, CEO, Procore Technologies

Pioneering a Cloud-Ready Construction Ecosystem

Aldridge Builds: Lake Shore Drive Bridge

MICHAEL MORRIS, SENIOR PROJECT MANAGER, ALRIDGE GROUP

Aldridge Builds: Lake Shore Drive Bridge

Embracing New Technologies to Address Systemic Challenges

William P. Silva, Director of Preconstruction, Swinerton

Embracing New Technologies to Address Systemic Challenges

Accelerated Bridge Construction Techniques Using Pre-Fabricated And Pre-Assembled Structural Systems

Sevak Demirjdjian, Vice President, Major Projects And Adel R. Zaki, Vice President/Chief Engineer, SNC Lavalin Inc

Accelerated Bridge Construction Techniques Using Pre-Fabricated And Pre-Assembled Structural SystemsSevak Demirjdjian, Vice President, Major Projects

Rationale for Implementing ABC Techniques for a Sustainable Bridge Construction

ABC Techniques have been used by SNC-Lavalin engineers throughout the years to ensure world-class bridge construction. Accelerated techniques for bridge construction should be used where the benefits have effects on the construction costs. This modern technology was used to implement innovative planning, design, materials, and construction methods in a safe and costeffective manner to reduce on-site construction. Decisions to use accelerated bridge construction techniques are made after considering the specific factors, mainly temporary roadways, temporary retaining structures, environmental impacts, sustainable development, user costs, social and financial prerogatives, long detours, and means and methods. The author has selected in this article, several structures where innovation and sustainability are paramount. Two major project applications are presented. The first consists of a new construction for two projects: an elevated roundabout and the new Champlain Bridge. The second describes the reconstruction of a footbridge and the replacement of bridge decks through different structural techniques.

Construction of an Elevated Roundabout

This is a complex geometry project located in a highly urbanized area. The project includes the relocation of public utilities, demolition of existing structures, construction of new structures and new roadways, and preparation of temporary roads and alternate itineraries for highway traffic, public transport, and pedestrian traffic. The elevated structure was constructed over a major highway in phases to maintain traffic flow.

Construction of a Footbridge

The construction entails the replacement of an existing footbridge. The ABC technique was implemented, which comprises HPC precast pre-stressed elements offering the most economical solution. The bridge spans 35m. The crosssection consists of two Z-shaped pre-cast girders with the shape providing a bottom ledge for supporting the pre-cast panels for the deck slab.

Reconstruction of the Jacqus-Cartier Bridge Deck Replacement–Integral Deck Floating System

Measuring 2.70 km span crossing a major river, with five lanes of traffic, this bridge carries more than 43 million vehicles every year, making it one of the busiest bridges in North America on a per lane basis. The ABC Technique for deck replacement was developed based on the following main objectives:

Minimize inconveniences to as many users as possible

Construct a highly durable deck (design service life greater than 50 years)

Minimize negative impacts on the environment

Reconstruction Of Princess Margaret Bridge–Intergral Deck, Composite Action

The Princess Margaret Bridge provides an elevated crossing over a major river, measuring 1097 m in overall length. It is a high-level structure supported on tall, slender piers to provide the required 23± m clearance for the center navigation span. The roadway is supported by nine deck truss spans, one through-truss navigation span, seven Plate Girder spans, and six Rolled Beam approach spans.

A composite section was created between the deck slab and the steel members. This composite action tremendously improved the capacity of those members and therefore reduced the need for strengthening.

Composite actions were created between the deck panels and top chord steel truss. The composite actions to the steel members were achieved through a spine beam that was detailed to connect either the Plate Girder top flange or the Deck Truss top chord to the deck panels after the post-tensioning operations.

New Champlain Bridge Corridor Crossing The StLawrence River

On October 5, 2011, the Government of Canada announced the replacement of the Champlain Bridge, one of the busiest crossings in Canada, carrying between 40 and 50 million vehicles per year.

The asymmetric, cable-stayed bridge features a 155-meter-high concrete tower and stay cables in a harp arrangement, an aesthetic element that designers felt would bolster the bridge’s place amongst the architecture of the cityscape. The three-corridor design of the project includes two three-lane roadways, a multi-use path for pedestrians and cyclists,as well as a two-lane transit artery that will accommodate a light-rail system. The overall construction timeline was a tight 42 months, which made for an accelerated schedule. Consequently, pre-cast elements played a major role in project planning and execution. Off-site pre-fabrication took some pressure off the on-site construction teamsso that crews could focus more directly on other construction components. Heavy gravitybased footing and pier starters for in-water approach spans with units weighing 800 to 900 metric tons were pre-fabricated on-site at a temporary pre-casting plant installed on an adjacent jetty. The units were then delivered to their final location using a custom-built gantry mounted on a large catamaran barge. The accelerated construction strategy was key to meeting the delivery schedule.

Conclusion

Accelerated techniques for bridge construction should be used where the benefits have effects on the construction costs. This modern technology was used to implement innovative planning, design, materials, and construction methods in a safe and cost-effective manner to reduce on-site construction. Decisions to use accelerated bridge construction techniques were made after considering the specific factors, mainly temporary roadways, temporary retaining structures, environmental impacts, sustainable development, user costs, social and financial prerogatives. In this article, the author has selected several bridge structures where the Accelerated Bridge Construction techniques were applied.

Read Also

Understanding the Rapidly Evolving Horizon of Inteligent Buildings

Understanding the Rapidly Evolving Horizon of Inteligent Buildings

Mitchell Britto, Director, Smart Building Services, TDIndustries
The UK's 2035 Net Zero-Carbon Challenge-The Role of the PM

The UK's 2035 Net Zero-Carbon Challenge-The Role of the PM

Andy Dunlop, Regional Lead Director PM, AECOM
The virus that made us Virtual

The virus that made us Virtual

Jorge Vazquez, Safety Director at MAREK
Agile Delivery of Semiconductor Facilities

Agile Delivery of Semiconductor Facilities

By Manuel Magg, Project Director, Exyte
Construction Risk is a Data Problem

Construction Risk is a Data Problem

Amias Gerety, Partner, QED Investors
follow on linkedin follow on twitter 2021 All Rights Reserved | by: constructiontechreview
Top